Progress Updates - 26885 Forest Blvd - Future Fire Station
September 28-October 2 - Scaffolding has been installed onsite, allowing structural masonry work for the new additions to move forward. CMU installation is progressing at the roof parapet. Mechanical, electrical, and plumbing work is ongoing. Roof demolition at the apparatus bays have started in preparation for the installation of the CMU, which will support the upcoming structural steel installation.
September 21-25 - Insulation and weather barrier are complete. The exterior stoops have been excavated, with backfilling and compaction. Sawcutting of the concrete floor is nearly complete. Mechanical, electrical, and plumbing work is ongoing.

September 14-18 - Footings and foundation walls have been poured. Foundation insulation and weather barrier installation are currently in progress. The stoops have been excavated, with forming and concrete placement underway. Demolition is ongoing inside; with wall demolition and sawcutting near completion. New wall openings are also being created.
September 7-11 - Concrete placement continues and foundation walls are being poured. Demolition inside began with removal of walls and the relocation of furniture and equipment.

August 31-September 4 - Began concrete placement for the addition footings. Foundation work continues. Our demolition contractor prepared to begin renovation work in the Fire Station office areas.
August 24-28 - Site work and excavation are complete. Equipment disconnects and salvage activities are underway as the team prepares for the apparatus area for renovation.
August 10-21 - Site work continues to move forward, including excavation and preparation for the new addition. Foundation work is expected to begin in early September, with construction of the addition continuing throughout the fall. Work is also beginning to prepare the existing Fire Station for renovations. Equipment and materials are being relocated as needed to allow construction activities to proceed.


