2024 Residential Street Improvement Project
Timeline: September 23, 2024 to Summer 2025 - Phase 2 begins April 21, 2025
This project was awarded to A-1 Excavating and began on September 23, 2024. It will be completed in 2 phases. Phase 1 consists of the rural section of roadways and two urban sections; this was substantially completed last year. Phase 2 consists of finalizing phase 1 and completing the remaining urban section of roads. Full project completion expected for early summer 2025.
About:
This project will include replacing the existing deteriorating pavements and curbs with new asphalt pavement and concrete curb and gutter (where existing curb exists only). See the list of affected streets below. Utility improvements include rehabilitation of the existing storm sewer inlets and installation of minor storm sewer improvements to improve area drainage.
Affected Streets:
- 258th Street - Goodview Ave to Goodwin Rd
- Goodwin Road - Verges Memorial Park to 25509 Goodwin Rd
- Goodwin Lane - Goodwin Rd to the southwest end
- Gramford Avenue - 256th St to Granada Ave
- 255th Street - Goodview Ave to 256th St (No curb)
- Grafton Avenue - 260th St to Gramford Ave (No curb)
- Granada Avenue - Gramford Ave to 260th St (No curb)
Street Parking Closed:
Vehicle access to driveways will be restored at the end of each working day. There may be times during construction that access along the project streets are limited during the daytime hours. Residents will be notified of impacts to access of individual driveways. Once concrete curb and concrete driveways are places, residents will need to park on the street for 1-week to allow it to cure and gain strength.
Stay Informed:
If you would like to receive updates on this project, please send an email to merichson@wsbeng.com.